A letter arrives at town hall, or a rumor spreads at the diner: a company wants to build a data center nearby. Within weeks, the town is being asked to decide something large, technical, and very hard to undo.
Our view at Mayor Town is simple. A data center is neither a gift nor a threat. It is a very large industrial customer that wants your land, your electricity, your water, and your goodwill. A town that negotiates well can get real value in return. A town that says yes on a handshake usually gets a brochure.
Why a Town Should Take the Question Seriously
It is tempting to refuse every proposal on reflex, and some towns will have good reasons to. But there are real reasons to at least listen and negotiate:
- Tax base. A large facility can add significant property tax revenue to pay for roads, schools, fire, and EMS, as long as the town does not give most of it away in abatements.
- Construction work. Brookings reports that a Microsoft campus in West Des Moines, Iowa has been credited with at least 3,000 construction jobs and 400 permanent positions.
- Grid and fiber upgrades. New substations, power lines, and fiber routes can also serve homes and businesses, if the agreement requires it.
- Computing close to home. A host town can negotiate access to AI capacity for its schools, library, clinics, and local government.
- Leverage that disappears. Your bargaining power is greatest before the zoning vote and the building permit. After that, you are asking for favors.
What the Evidence Says About the Risks
A fair look has to include the other side. Recent policy research points to several problems:
- Fewer permanent jobs than expected. A Federation of American Scientists (FAS) policy memo reports that operating data centers employ about 157 permanent workers on average, and that in the subsidy programs it examined, public subsidies came to between $1.4 million and $2.1 million per permanent job. Ask for jobs in writing, but never let permanent job counts be the main reason for a yes.
- Pressure on power bills. Very large electricity customers force utilities to build new generation and lines. Unless the rules say otherwise, other customers can end up sharing those costs. The same memo points to regions with data center growth where electricity prices have climbed sharply.
- Water, noise, and backup generators. Some facilities use millions of gallons of water a day for cooling, according to the Ohio Consumers’ Counsel. Diesel backup generators add air pollution and noise.
- Secrecy. FAS found that only 11 of the 36 states with data center subsidy programs publicly disclose which companies receive them.
Communities are responding. In its September 2026 guide for local governments, FAS reports that 33 of the 42 local data center ordinances and ballot measures it reviewed were passed in 2026 alone, compared with two in 2024 and six in 2025. Many towns are pausing to write rules first. That is a sensible model.
The Rule: If It Is Not in a Signed Contract, It Is Not a Promise
Press releases, slide decks, and verbal assurances do not bind anyone. Every commitment below must appear in a written agreement, with specific numbers, specific dates, and a penalty if the company misses them.
A caution from the field: When FAS searched for executed data center community agreements, the only fully executed and publicly posted one it found at the time was in Lancaster, Pennsylvania. It covers many topics, including transparency, water, energy, noise, and decommissioning, but FAS observed that much of the substance appears to be left to be decided later. A long list of topics is not protection. Numbers and penalties are.
The Five Commitments to Demand
| Commitment | What to put in writing | How it is enforced |
|---|---|---|
| Jobs | Permanent and construction job counts, a wage floor, benefits, and a timeline, kept for the life of the facility | Annual verified reports; repayment of tax breaks or fixed damages for each missing job |
| Local hiring | First chance at openings for local applicants, a local-hire target, and training slots tied to the school or college | Monthly hiring reports during construction; contractors bound by the same terms |
| Power grid | Company pays for its own connection and upgrades; minimum payments whether or not power is used; emergency-use power for town facilities | Financial guarantees; recorded agreement; intervention at the state utility commission |
| Free AI access | Named groups, stated monthly amounts, current-quality service, privacy protections, and a term as long as the facility runs | Penalties and loss of tax breaks if the allotment is cut |
| Water, noise, closure | Water cap and reporting, noise limits at the property line, and a bond to clean up and remove the facility | Independent monitor; bond or letter of credit sized to the penalties |
1. Jobs
Ask for a number, not a hope. The agreement should state how many permanent full-time jobs and how many construction jobs the company will create, the minimum wage and benefits, and the date by which they will exist. Define what counts as a job, including whether on-site contractors such as security and maintenance are included, so the number cannot be padded.
Then attach a consequence. State incentive programs commonly tie tax breaks to job counts and wage floors, and many require repayment if the targets are missed, according to the National Conference of State Legislatures. Your local agreement should do the same: repay abated taxes, or pay a fixed sum for each missing job.
Because permanent job counts at these facilities tend to be modest, also ask for things that last: paid apprenticeships, training programs with the community college, and a commitment to buy goods and services from local businesses.
2. A Preference for Local Hires
- First-source hiring. The company posts openings with the local workforce office and the community college before advertising widely, and interviews every qualified local applicant.
- A defined local-hire target for construction and for permanent jobs, with “local” clearly defined, for example residents of the town and surrounding county.
- Training pipeline. The company funds or partners on training so local people can actually qualify for the jobs.
- Prevailing wages for construction work, and the same hiring terms passed down to every general contractor and subcontractor.
- Reporting. Monthly hiring reports during construction, and quarterly after opening, open to the public.
One legal caution: what a town may require on residency-based hiring varies by state, and hard quotas can be challenged. Have your town attorney confirm the structure that is lawful where you are. First-source and training commitments are often easier to defend than a rigid quota.
3. Investment in the Power Grid
The principle is easy to state: the companies that benefit from the data center pay for what it takes to power it, and nobody else’s bill goes up because of it.
- The company pays the full cost of its connection, substations, and line upgrades.
- Minimum payments. In Ohio, regulators approved a tariff requiring new data centers above 25 megawatts to pay for at least 85 percent of their subscribed power capacity for up to 12 years, whether or not they use it. That is a useful model of what “paying their own way” looks like.
- Financial guarantees and exit fees, so if the project is canceled, other customers are not left with the bill for equipment that was never used.
- Emergency-use power and fiber. The company agrees that backup power and network connections can serve the shelter, town hall, and clinic in a declared emergency.
- Limits on diesel generators for running hours and emissions, and a commitment to reduce power use during grid emergencies.
- Public reporting of monthly electricity and water use.
Electric rates are usually set by the state utility commission, not by the town. So do three things: write the same protections into your own agreement, speak up in the commission’s proceedings, and meet with your electric utility early, before the company does.
4. Free AI Access for Residents, Schools, and Businesses
A data center exists to produce AI computing. If a town hosts the building, the town should share in the product. This is an unusual ask, because most agreements do not include it, so raise it at the first meeting and put a dollar value on it. Be specific, because the word “generous” has no legal meaning:
- Who is covered: every resident with a local address, every public and private school, the public library, and local small businesses, with “small business” defined.
- How much: a stated monthly allotment per person, per school, and per business, in plain units, with a floor that can never be reduced and an increase as computing gets cheaper.
- What quality: current-generation service, not a stripped-down version, with reserved capacity so local users are not pushed aside.
- How long: for as long as the facility operates, and binding on any future owner.
- Privacy: no selling of residents’ usage data, no advertising built on it, and no use of student information beyond what the law and the school district allow.
- Access for everyone: sign-up through the library and the schools, not only online, with free classes so older residents can learn to use it with confidence.
- Who runs it: the town or school district names the administrator, and the company pays the administration costs.
- Enforcement: if the allotment is cut or the quality drops, the company pays a penalty or loses its tax breaks.
5. Water, Noise, Land, and the Day It Closes
- Water. Set a daily cap and require public reporting. One agreement described by FAS capped municipal water use at 20,000 gallons per day per campus. Add drought rules that reduce use when your town is short.
- Noise and lighting. Measure at the property line against the level before construction, and require shielded lighting.
- Decommissioning. Require a bond or letter of credit so the town is never left with an empty building to remove.
- Tax breaks. Be careful with long abatements. Brookings notes, for example, that El Paso, Texas agreed to an 80 percent property tax abatement over 35 years for a $1.5 billion Meta data center. Whatever you grant, tie it to performance and make it repayable.
Making It Legally Binding
Promises are only as strong as the contract that holds them. When your attorney drafts the agreement, insist on these points:
- Sign with the parent company as well as the local operating company. A newly formed LLC can be dissolved. Require a parent guarantee.
- Tie it to the approvals. Make the agreement a condition of the rezoning or special-use permit and record it against the property, so it binds future buyers.
- Put money behind it: a bond or letter of credit, repayable tax breaks, and fixed damages for each missed target.
- Use numbers and dates. Strike phrases like “good faith efforts” and “commercially reasonable.”
- Independent monitoring. An outside monitor, paid by the company, reports to the public every year, with the town’s right to audit.
- Real remedies: the right to stop work, to terminate, and to recover the town’s legal costs if it prevails.
- A community advisory board with actual authority to review reports and call for corrections.
- Your own advisors. Hire your own attorney and technical consultants, and have the applicant fund them through an escrow account.
- No gag orders. Do not sign a confidentiality agreement that keeps you from informing residents.
A Sensible Sequence for the Town
- Pause. Adopt a short, time-limited hold on applications while you write rules.
- Update the zoning. Treat data centers as a special use, with setbacks and limits on noise and water use.
- Learn the facts. Ask the utility how much power is requested, ask the water district what it can supply, and ask the state commission how large customers are billed.
- Hold public meetings early, in plain language, before any vote.
- Negotiate with your own counsel, and publish the draft agreement for public comment.
- Vote only on a signed agreement with every commitment attached.
- Monitor every year, and publish the results.
When the Answer Should Be No
A firm no is a legitimate outcome. Walk away, or keep the pause in place, if the company:
- Will not put job, hiring, grid, and AI-access numbers in a signed agreement.
- Will not provide a parent-company guarantee or financial security.
- Wants other customers to share the cost of grid upgrades.
- Refuses to disclose expected water and power use.
- Demands secrecy, or a vote before the community has seen the terms.
The Mayor Town Angle: Resilience
A well-negotiated data center can strengthen what Mayor Town cares about most. It brings power infrastructure, fiber, and computing capacity into the community, and the right agreement can make all three available to the town in an emergency. It also fits our argument that towns should own more of their own technology. See our posts on the Municipal AI Hub, on-premises AI for emergency readiness, and energy sovereignty.
The bottom line: consider it, study it, and negotiate it as if you will have to live with the result, because you will.
Sources and Further Reading
- Federation of American Scientists: Empowering Communities through Community Benefit Agreements in AI-Fueled Data Center Development
- Federation of American Scientists: Before Breaking Ground, a local government guide to data center policy (September 2026)
- Federation of American Scientists: data center community benefit agreements, including Lancaster, Pennsylvania
- Brookings: Why community benefit agreements are necessary for data centers
- National Conference of State Legislatures: Subsidizing Servers, how states compete to attract data centers
- POWER Magazine: Regulator approves AEP Ohio’s landmark data center tariff
- Office of the Ohio Consumers’ Counsel: Quick Facts, Data Centers in Ohio (PDF)
This post is general information, not legal advice. Laws on development agreements, hiring preferences, and utility rates differ by state. Work with your town attorney before signing anything.